NAME OF PROJECT: MUDANJIANG WATER SUPPLY
Project No.: PRC36006-01
Executing Agency: Mudanjiang Municipal Government
No. 12 Xinhua Road, Mudanjiang City, Heilongjiang,
PRC 157011
Contact: Mr. Wang Bao Liang, Vice-Mayor
Fax: 86-453-652 5430/692 5611
Tel. No.: 86-453-652 3091/693 9021
Loan Amount: US$25.0 Million
Sector/Subsector: Social Infrastructure/Water Supply
and Sanitation
Objectives and Scope: The objectives of the Project
are to (i) improve the water quality problems in
Mudanjiang and meet future water demands; (ii) improve
public health by providing clean treated water;
(iii) promote long-term urban development in Mudanjiang;
(iv) institutional strengthening of MLWSCC for commercial
operation and maintenance of the new system; and
(v) tariff reforms to achieve full cost recovery.
The scope of the Project includes two water treatment
plants with a capacity of 200,000 m3/day, distribution
network and associated pumping stations.
Procurement:
Goods: To be determined.
Services: To be determined.
Environmental Category: To be determined.
Project Processing Stage:Beginning of Fact-finding
Mission: Jul 2002.
Project Officer: Sangay Penjor; Tel.: (63-2) 632-6298,
Social Sectors Division, ECRD
In-country Commercial Officer: Thomas Boam, Senior
Commercial Officer, American Embassy, Beijing
(ORIGIN: SBALLARD-CS/ADB) RICCIARDONE
NEW PROJECT
PREPARATORY TECHNICAL ASSISTANCE FOR CHINA,
APRIL 2002
NAME OF PROJECT:
MUDANJIANG WATER SUPPLY
Project No.: PRC36006-01
Executing Agency: Mudanjiang Municipal Government
No. 12 Xinhua Road, Mudanjiang City, Heilongjiang,
PRC 157011
Contact: Mr. Wang Bao Liang, Vice-Mayor
Fax: 86-453-652 54 30/692 56 11
Tel: 86-453-652 3091/693 90 21
TA Amount : US$150.0 Thousand
Sector/Sub-sector: Social Infrastructure/Water Supply
and Sanitation
Objectives and Scope: The objective
of the TA is to formulate a viable water supply
suitable for ADB financing to provide improved drinking
water for the City of Mudanjiang. The scope of the
TA covers the activities needed to assess the revised
Project, including review of the feasibility study
report and environmental assessment prepared by
the Government.
Consulting Services: The international
and domestic consultants will have expertise in
(i) water supply and management / water treatment
/ institutional development / environmental impact
assessment; (ii) social development / poverty reduction
/ gender issues / community participation; and (iii)
economic and financial analysis.
Recruitment of Consultants: Recruitment
of consultants expected to take place on June 2002.
Project Officer: Sangay Penjor; Tel.:
(63-2) 632-6298, Social Sectors Division, ECRD
In-country Commercial Officer: Thomas Boam, Senior
Commercial Officer, American Embassy Beijing
The People's Republic of China has
received a loan from the Asian Development Bank
(ADB) to cover part of the cost of its Acid Rain
Control and Environmental Improvement Project. The
Project will finance investments to improve air
quality in four secondary cities (Guichi, Huangshan,
Tonglin and Wuhu).
The objective of the Project is to
control acid rain and improve the environment in
the Yangtze River Valley in Anhui Province. The
Project will promote cleaner production, reduce
waste, improve energy efficiency, enhance environmental
quality, and strengthen institutions for environmental
management.
The Project has three main components:
(i) six subprojects for promoting cleaner production
undertaken by industrial enterprises; (ii) three
environmental improvement and acid rain damage rehabilitation
subprojects in two ecologically protected areas
(Huangshan and Juihua); and (iii) institutional
strengthening of provincial and local environmental
agencies, and subproject enterprises.
Consulting Services:
Consultants will provide training and
capacity building in environmental monitoring, enterprise
governance, financial management, detailed design
and construction supervision, and project management.
The Executing Agency for the Project
will be the Anhui Provincial Government.
Anhui Provincial Government
Administrative Office
Anhui Environment Protection Bureau
No. 85 West Changjiang Road
Hefei City, Anhui Province
People's Republic of China
Fax No. 86-551-2822745; 86-551-2601424
Tel. No. 86-551-260-2209
PRC-GEF Partnership on Land Degradation
Feb 7, 2002
Asian Development Bank (ADB) convened
a meeting of international donors to review a $1
billion+, 10-year program between GEF and China
to combat land degradation in dryland ecosystems.
Other intended benefits are poverty alleviation
and lessons for institutional and policy strengthening.
ADB and World Bank each expect to put in $500 million
over the course of the project, and are interested
in soliciting additional donations. Most of the
money is loans, but there will probably be up to
$25 million in grants and technical assistance.
An inception report is due by February
18, 2002. A team of international and Chinese consultants
will begin in March, 2002 to evaluate needs and
pick potential sites for pilot studies. They plan
to produce a program framework, driven by Chinese
evaluations, by June that will:
lay out general policies;
identify
priority ecosystems;
include a prioritized list of possible investments; and
specify
milestones, indicators, and outcomes.
They want a sustained
focus on land degradation (hence the long time frame of the project), and to link
that to existing Chinese initiatives on biodiversity and desertification.
Websites
www.adb.org/projects/PRC_GEF_Partnership
www.gefchina.org.cn
Asian
Developmental Bank and World Bank Environmental Projects in China
CHINA
LIAO RIVER BASIN PROJECT-World Bank
LOAN AMOUNT: -US$100 million equivalent
PROJECT DESCRIPTION: The project will reduce pollution and
increase quality to a minimum of "Class V" (agricultural water supply
or general amenity use) water quality throughout the Basin by 2010 by (1) regulating
and reducing pollution from industries; (2) priority wastewater treatment works
in all cities in the river basin; (3) improving collection and disposal of sludge
from wastewater treatment plants; (4) protecting water used for agriculture and
aquaculture; (5) improving water quality in the Bohai sea. Other initiatives may
include reducing overall per capita water demand, adopting water conservation
measures and public outreach programs.
For more information,
call Miriam Razaq at (202) 458-2939 or e-mail mrazaq@worldbank.org, or visit http://www4.worldbank.org/sprojects
Tian
Jin Waste Water Treatment Tender from the ADB
China has received
a loan from ADB towards the cost of the Tianjin Wastewater Treatment and Water
Resources Protection Project, the main objective is to construct a new Wastewater
Treatment plant with the A/O Treatment process in Beicang service area of urban
Tianjin. The subproject will provide trunk sewers and four sewage pump stations,
and a wastewater treatment plant
US firm may find opportunities
in the M&E for Wastewater Treatment Plant including:
(i)
treatment equipment for sewage, including pumps, lifting equipment, gates, valves;
(ii) treatment equipment for sludge, including pre-thickening tank, sludge
digester, sludge control room, gas holder, pumps, valves, gas boiler, laboratory
equipment, communication equipment and heating boiler;
(iii) electrical, instrumentation
and automation equipment, including 10KV substation, control room of inlet pumping
station, blower room, chlorination room, control room of nitrogen removal room,
high voltage switch gear;
(iv) automation system
Procurement
Agency:
China National Industrial Machinery Import and Export
Company
23 Floor of West Wing of Sichuan Mansion
1 Fuwaidajie Avenue
Beijing,
China 100037
Tel. 86-10-68991111; 68991215
Fax: 86-10-68991200; 68314137
E-mail:
caixj@cmc.com.cn
World Bank- $800 Million Loan for Environmental
Protection in Shanghai
During its 10th Five Year Plan, Shanghai
aims to invest at least 3% of its GDP on environmental infrastructure in the following:
(a) urban wastewater collection and disposal coverage extended from 68 percent
to closer to complete coverage in the greater metropolitan area; (b) urban wastewater
treatment expanded from the current 44 percent to 70 percent in the metropolitan
area; (c) reduction of COD by 10t or 31, 500 tons/year; (d) solid waste managed
with 60 percent of domestic garbage collected and treated in the urban areas by
2003, and 90 percent by 2005 compared to 30 percent at present, and in the rural
areas, 30 percent of garbage collected by 2003, and 80 percent by 2005 compared
to low percent at present; and (e) forestation of 28-30 percent in Shanghai City
from the current level of 22 percent.
The total amount of loans
under the proposed Adjustable Project Loan is expected to be about $700 million
grouped into 3 phases of $250, $250 and $200 million. The first phase would concentrate
on urban environment, including wastewater collection, treatment and disposal,
improvements to solid and hazardous waste management, and information technology.
The second phase would focus on suburban environment improvements, in both wastewater
and solid waste management.
The loan should be finalized in 6/2002 so
companies interested in these projects should get involved now. (see: Solid Waste
Equipment Show information in exhibition Section).
Contact
DC Consultants for additional information.
Shanghai¡¯s
Suzhou Creek Rehabilitation Project
The clean-up effort
of Shanghai¡¯s Suzhou creek, which flows through the city, is the largest of Shanghia¡¯s
environmental projects. The city has pledged $1 billion, including a $300 million
loan from the Asian Development Bank, to clean up the river and install sewer
infrastructure in surrounding areas. Over the last three years about $169 million
has been spent on the project thus far.
Shanghai appears to
have decided to dredge the creek¡¯s toxic sludge for disposal similar to the clean-up
of the PCB contaminated Hudson River in New York. Foreign assistance will be needed
on the treatment of sludge. Treatment options being discussed are the building
of a dedicated facility for the treatment and disposal of hazardous waste, converting
into fertilizer, or used in the making of construction materials.
Contact
DC Consultants for additional information.
USD150
million loan project for China's ACID Rain Control Project
This
project was approved by the Asian Development Bank.
For more information:
Stewart Ballard Stewart at (63-2) 887-1345.
The Project will
finance investments to improve air quality in four secondary cities (Guichi, Huangshan,
Tongling, and Wuhu), addressing acid rain and air pollution problems in the part
of the Yangtze River Valley that lies within Anhui Province by the (i) promotion
of cleaner production, energy efficiency and waste minimization in six industries
to reduce SO2 and other sources of acid rain, (ii) three environmental improvement
and acid rain damage rehabilitation subprojects in two ecologically protected
areas and (iii) institutional strengthening of environmental management and monitoring
agencies in the project area and subproject enterprises.
ADB
will provide a loan of $150 million to finance the entire foreign exchange cost
of the Project. The local currency financing of $175 million equivalent will be
arranged through domestic borrowing ($69.2 million equivalent), enterprise contribution
($97 million), and from Provincial and municipality governments ($8.8 million).
EXECUTING
AGENCY:
Anhui Provincial Government (APG)
4th Floor, South
Building
221 Middle Changjiang Road
Hefei, Anhui 230001
Contact: Pan
Tiansheng, Director
Fax: (86-551) 2602208
Tel.: (86-551) 2602208